Comparing project alternatives in money terms: time value of money, cost analysis and choosing between options under uncertainty.

Exam weight
5%
On a real exam
≈ 6 questions
In our bank
30 questions

Topics that come up most

  • Present worth, future worth and annual worth
  • Interest factors and cash-flow diagrams
  • Life-cycle and incremental cost analysis
  • Depreciation and break-even analysis
  • Sensitivity and uncertainty in economic decisions

How to study it

Sketch a cash-flow diagram before every problem and use the interest factor tables in the Reference Handbook. That cuts out most sign and timing errors.

Sample Engineering Economics questions

Try each one before opening the answer. Original questions written to the official exam objectives.

  1. Question 1

    At an interest rate of 6% compounded annually, what is the present worth of a $50,000 salvage value received at the end of year 10?

    • A$27,920
    • B$31,250
    • C$20,000
    • D$3,793
    Show answer and explanation

    Answer: A) $27,920

    A single future amount is brought back to the present with the single-payment present-worth factor: P = F(1 + i)^−n = 50,000 × 0.5584 ≈ $27,920.

    • ACorrect. P = F/(1 + i)^n = 50,000/(1.06)^10 = 50,000 × 0.5584 ≈ $27,920.
    • BIncorrect. This discounts with simple interest, 50,000/(1 + 0.06 × 10) = 50,000/1.6. Present worth calls for compound discounting.
    • CIncorrect. This takes 6% of the face value for each of 10 years off the amount, 50,000 × (1 − 0.60). That is not a valid discounting method.
    • DIncorrect. This uses the sinking-fund factor (A/F, 6%, 10) = 0.0759. That gives the equal annual deposit needed to build up $50,000, not a single present amount.
  2. Question 2

    At 5% interest, the present worth of $1,000,000 needed in 10 years is about:

    • A$1,628,900
    • B$500,000
    • C$613,900
    • D$952,400
    Show answer and explanation

    Answer: C) $613,900

    • AIncorrect. That's the future worth.
    • BIncorrect. That's simple discounting at 5% for 10 years.
    • CCorrect. P = 1,000,000/(1.05)¹⁰ = 1,000,000/1.6289.
    • DIncorrect. That's one year of discounting.
  3. Question 3

    A $1 million plant is financed at 8% over 20 years. With (A/P, 8%, 20) = 0.1019, the annual capital recovery is about:

    • A$80,000
    • B$50,000
    • C$101,900
    • D$9,813,000
    Show answer and explanation

    Answer: C) $101,900

    • AIncorrect. That's interest only.
    • BIncorrect. That ignores interest.
    • CCorrect. 1,000,000 × 0.1019.
    • DIncorrect. Multiply by A/P, don't divide.
  4. Question 4

    A treatment chemical contract costs $10,000 today. If its cost rises with inflation at 3% per year, compounded annually, what will it cost 10 years from now?

    • A$13,000
    • B$13,439
    • C$10,300
    • D$7,441
    Show answer and explanation

    Answer: B) $13,439

    Inflated future cost uses the compound-amount relationship F = P(1 + f)^n: 10,000 × (1.03)^10 ≈ $13,439.

    • AIncorrect. This applies simple inflation, 10,000 × (1 + 0.03 × 10). Inflation compounds each year.
    • BCorrect. F = P(1 + f)^n = 10,000 × (1.03)^10 = 10,000 × 1.3439 ≈ $13,439.
    • CIncorrect. This applies only one year of inflation instead of ten.
    • DIncorrect. This divides by (1.03)^10, which discounts the cost back in time instead of inflating it forward.
  5. Question 5

    A $2 million treatment plant with a $200,000 salvage value is depreciated straight-line over 20 years. Annual depreciation is:

    • A$110,000
    • B$100,000
    • C$90,000
    • D$9,000
    Show answer and explanation

    Answer: C) $90,000

    • AIncorrect. Subtract, don't add, salvage.
    • BIncorrect. Subtract salvage first.
    • CCorrect. (2,000,000 − 200,000)/20.
    • DIncorrect. Recheck the division.
  6. Question 6

    A project costs $100,000 and returns $30,000 per year for 5 years. At 10%, with (P/A, 10%, 5) = 3.791, its net present worth is about:

    • A$13,730
    • B$50,000
    • C$113,730
    • D$7,910
    Show answer and explanation

    Answer: A) $13,730

    • ACorrect. 30,000(3.791) − 100,000.
    • BIncorrect. That ignores interest.
    • CIncorrect. Subtract the initial cost.
    • DIncorrect. Recheck the multiplication.
  7. Question 7

    Two wastewater treatment alternatives have equal service lives but different capital costs and different annual operation and maintenance (O&M) costs. Which criterion should be used to select the more economical alternative?

    • ALowest initial capital cost of each alternative
    • BLowest equivalent annual cost over the study period
    • CLowest O&M cost in the first year of operation
    • DShortest simple payback period on the capital cost
    Show answer and explanation

    Answer: B) Lowest equivalent annual cost over the study period

    Compare alternatives on a life-cycle basis, such as equivalent annual cost or present worth, which discounts capital and all O&M costs to a common time basis. Then choose the alternative with the lowest life-cycle cost.

    • AIncorrect. Looking only at first cost ignores O&M costs over the whole service life, and those can outweigh differences in capital cost.
    • BCorrect. Equivalent annual cost (or present worth) converts capital cost and every future O&M cost to a common time basis using the interest rate, so the alternative with the lowest life-cycle cost is the most economical.
    • CIncorrect. One year of O&M leaves out the capital cost and the O&M costs in all later years.
    • DIncorrect. Simple payback ignores the time value of money and any costs after the payback point, so it doesn't measure total life-cycle cost.
  8. Question 8

    A piece of treatment equipment cost $2.0 million when the applicable cost index was 800. The index is now 1,000. Using the cost index, the estimated current cost of the equipment is closest to:

    • A$1.6 million
    • B$2.0 million
    • C$2.4 million
    • D$2.5 million
    Show answer and explanation

    Answer: D) $2.5 million

    Cost indexes scale a historical cost by the ratio of the current index to the original index: $2.0M × 1,000/800 = $2.5M.

    • AIncorrect. This flips the index ratio (2.0 × 800/1,000). The index went up, so the cost should go up too.
    • BIncorrect. This ignores the change in the cost index. Historical costs must be brought up to the current index.
    • CIncorrect. This divides the 200-point rise by the new index (20%) instead of the original index (25%). The correct escalation is 2.0 × (1 + 200/800).
    • DCorrect. Current cost = original cost × (current index / original index) = 2.0 × 1,000/800 = $2.5 million.
  9. Question 9

    Which approach correctly describes a life-cycle cost analysis of a proposed water treatment facility?

    • ACapital, O&M and replacement costs, less salvage value, discounted to present worth
    • BCapital and O&M costs over the facility life, summed in nominal dollars without discounting
    • CCapital, O&M and replacement costs, discounted to present worth, with salvage value ignored
    • DCapital cost plus first-year O&M cost, discounted to present worth at the MARR
    Show answer and explanation

    Answer: A) Capital, O&M and replacement costs, less salvage value, discounted to present worth

    A life-cycle cost analysis takes capital, O&M, energy and replacement costs over the study period, subtracts salvage value, and discounts everything to present worth (or an equivalent annual cost).

    • ACorrect. Life-cycle cost includes investment cost, operation and maintenance, energy, and replacement costs over the study period, minus salvage value. All of these are discounted to present value so alternatives can be compared on the same basis.
    • BIncorrect. Adding future costs without discounting ignores the time value of money. Life-cycle cost analysis converts future costs to present values.
    • CIncorrect. Salvage (residual) value at the end of the study period is a credit that is subtracted from investment and replacement costs. Leaving it out misstates the life-cycle cost.
    • DIncorrect. Using only the first year of O&M leaves out operating, maintenance and replacement costs for the rest of the facility's life.
  10. Question 10

    A project has a present worth of benefits of $3 million and costs of $2 million. Its benefit-cost ratio is:

    • A1.5
    • B0.67
    • C1.0
    • D5.0
    Show answer and explanation

    Answer: A) 1.5

    • ACorrect. 3/2; above 1 is justified.
    • BIncorrect. That's inverted.
    • CIncorrect. That's B − C in millions.
    • DIncorrect. Divide, don't add.

Engineering Economics: FAQs

How much of the FE exam is Engineering Economics?

Engineering Economics is 5% of the FE exam by the official exam guide's weighting, which on a 110-question form works out to roughly 6 questions. The real exam's exact split varies by form.

What does the Engineering Economics domain cover?

Comparing project alternatives in money terms: time value of money, cost analysis and choosing between options under uncertainty.

How should I study Engineering Economics for FE?

Sketch a cash-flow diagram before every problem and use the interest factor tables in the Reference Handbook. That cuts out most sign and timing errors.

Where can I practise more Engineering Economics questions?

This page has 10 free Engineering Economics questions with answers. The ExamWize FE question bank has 30 questions in this domain. Every practice exam result breaks your score down by domain, and Review Mode re-drills the questions you missed.

Get Engineering Economics exam-ready

The full FE bank has 30 Engineering Economics questions. Timed practice exams match the real exam's length and domain weights, every result shows your score per domain, and Review Mode re-drills the questions you missed.

Not affiliated with NCEES; questions are original, written from the official exam outline, and never copied from the real exam.