Engineering Economics practice questions
10 free Engineering Economics questions for the FE Electrical and Computer Exam (FE) exam, each with the correct answer and an explanation for every option.
What this domain covers
Comparing engineering options in money terms: time value of money, cost estimation and simple decision analysis.
- Exam weight
- 5%
- On a real exam
- ≈ 6 questions
- In our bank
- 30 questions
Topics that come up most
- Present, future and annual worth
- Interest factors and cash-flow diagrams
- Break-even and payback analysis
- Depreciation methods
- Cost estimation and risk
How to study it
Draw a cash-flow diagram for every problem before picking an interest factor, and get comfortable reading the Handbook's interest tables.
Sample Engineering Economics questions
Try each one before opening the answer. Original questions written to the official exam objectives.
Question 1
With 3% annual inflation, an item costing $100 today will cost about how much in 10 years?
- A$103
- B$130
- C$134
- D$174
Show answer and explanation
Answer: C) $134
- AIncorrect. That's one year.
- BIncorrect. That's simple growth.
- CCorrect. \(100(1.03)^{10}\).
- DIncorrect. Recheck the exponent.
Question 2
Equipment costs $20,000, has a $2,000 salvage value and a 6-year life. Its straight-line depreciation is:
- A$3,000 a year
- B$3,333 a year, ignoring salvage
- C$2,000 a year
- D$18,000 a year
Show answer and explanation
Answer: A) $3,000 a year
- ACorrect. ($20,000 − $2,000) ÷ 6.
- BIncorrect. Salvage reduces depreciation.
- CIncorrect. That isn't the calculation.
- DIncorrect. That's the total depreciable amount.
Question 3
Motor B costs $1,000 more than motor A but saves $250 per year. Ignoring interest, the payback period is:
- A4 years
- B0.25 years
- C2.5 years
- D10 years
Show answer and explanation
Answer: A) 4 years
- ACorrect. $1,000 ÷ $250 per year = 4 years.
- BIncorrect. That's inverted.
- CIncorrect. Recheck the division.
- DIncorrect. Recheck the division.
Question 4
A high-efficiency motor saves $500 per year for 10 years. At 8%, the present worth of the savings is about:
- A$7,243
- B$5,000
- C$3,355
- D$4,000
Show answer and explanation
Answer: C) $3,355
- AIncorrect. That's a future worth.
- BIncorrect. That ignores interest.
- CCorrect. \(500(P/A, 8\%, 10) = 500(6.7101)\).
- DIncorrect. Recheck the series factor.
Question 5
A nominal 10% annual rate compounded quarterly gives an effective annual rate of about:
- A10.38%
- B10.00%
- C2.50%
- D10.25%
Show answer and explanation
Answer: A) 10.38%
- ACorrect. \((1.025)^4 - 1\).
- BIncorrect. Quarterly compounding raises it.
- CIncorrect. That's the quarterly rate.
- DIncorrect. That's semiannual compounding.
Question 6
Equipment costs $10,000 and has a $2,000 salvage value in 5 years. At 10%, its net present cost is about:
- A$9,000
- B$8,000
- C$11,242
- D$8,758
Show answer and explanation
Answer: D) $8,758
- AIncorrect. Recheck the discount factor.
- BIncorrect. Discount the salvage value.
- CIncorrect. Subtract the salvage value.
- DCorrect. 10,000 − 2,000(0.6209).
Question 7
An upgrade costs $12,000 and saves $3,000 a year. Ignoring interest, its simple payback period is:
- A36 years
- B0.25 years, inverting the ratio
- C4 years
- D9 years
Show answer and explanation
Answer: C) 4 years
- AIncorrect. That multiplies instead.
- BIncorrect. That reverses it.
- CCorrect. $12,000 ÷ $3,000.
- DIncorrect. That subtracts instead.
Question 8
A $50,000 loan at 8% annual interest is repaid in 10 equal end-of-year payments. Each payment is closest to:
- A$9,000
- B$5,000
- C$7,451
- D$3,451
Show answer and explanation
Answer: C) $7,451
Equal payments that repay a present amount come from the capital recovery factor: A = P(A/P, 8%, 10) = $50,000 × 0.14903 ≈ $7,451.
- AIncorrect. This adds 10 years of simple interest ($40,000) to the principal and divides by 10. It ignores that the balance, and so the interest owed, falls as the loan is paid down.
- BIncorrect. $50,000/10 repays only the principal and leaves out interest entirely.
- CCorrect. A = P(A/P, 8%, 10) = $50,000 × [0.08(1.08)^10/((1.08)^10 − 1)] = $50,000 × 0.14903 ≈ $7,451.
- DIncorrect. This uses the sinking-fund factor (A/F, 8%, 10) = 0.06903, which treats $50,000 as a future amount rather than a present loan.
Question 9
Which statement best describes a key weakness of the simple (undiscounted) payback period method for comparing projects?
- AIt ignores the time value of money and cash flows after payback
- BIt requires an assumed discount rate before it can be computed
- CIt tends to favor projects with long payback periods
- DIt double-counts depreciation in the annual net cash flows
Show answer and explanation
Answer: A) It ignores the time value of money and cash flows after payback
Simple payback ignores the time value of money and any cash flows after the payback point, so it can favor quick-payback projects even when they are less profitable.
- ACorrect. Simple payback just adds up undiscounted cash flows until the investment is recovered. Anything earned after that point is ignored, so it can favor short-lived projects over more profitable long-lived ones.
- BIncorrect. Simple payback uses no interest rate. Discounted payback is the variant that needs one.
- CIncorrect. It does the opposite: it ranks projects that recover their cost quickly higher.
- DIncorrect. Depreciation handling depends on how the cash flows are prepared, not on the payback method. Its real weakness is ignoring timing and later cash flows.
Question 10
An engineer will receive $2,000 at the end of each year for 15 years. At an interest rate of 7% per year, compounded annually, what is the present worth of this series?
- A$10,873
- B$30,000
- C$18,216
- D$50,258
Show answer and explanation
Answer: C) $18,216
Use the uniform-series present worth factor: P = A(P/A,i,n) = 2,000 × 9.1079 ≈ $18,216. The other values come from not discounting, discounting as a single lump sum, or computing future worth.
- AIncorrect. This treats the $30,000 total as one lump sum received at year 15 and discounts it with (P/F,7%,15) = 0.3624. The payments actually arrive every year, so the uniform-series factor is needed.
- BIncorrect. This is the undiscounted sum, 15 × $2,000. It ignores the time value of money.
- CCorrect. P = A(P/A,7%,15) = 2,000 × [1 − 1.07^−15]/0.07 = 2,000 × 9.1079 ≈ $18,216.
- DIncorrect. This is the future worth at year 15: F = 2,000 × (F/A,7%,15) = 2,000 × 25.129. The question asks for the present worth.
Engineering Economics: FAQs
How much of the FE exam is Engineering Economics?
Engineering Economics is 5% of the FE exam by the official exam guide's weighting, which on a 110-question form works out to roughly 6 questions. The real exam's exact split varies by form.
What does the Engineering Economics domain cover?
Comparing engineering options in money terms: time value of money, cost estimation and simple decision analysis.
How should I study Engineering Economics for FE?
Draw a cash-flow diagram for every problem before picking an interest factor, and get comfortable reading the Handbook's interest tables.
Where can I practise more Engineering Economics questions?
This page has 10 free Engineering Economics questions with answers. The ExamWize FE question bank has 30 questions in this domain. Every practice exam result breaks your score down by domain, and Review Mode re-drills the questions you missed.
Other FE topics
- Mathematics11% of the exam
- Probability and Statistics4% of the exam
- Ethics and Professional Practice4% of the exam
- Properties of Electrical Materials4% of the exam
- Circuit Analysis (DC and AC Steady State)11% of the exam
- Linear Systems5% of the exam
- Signal Processing5% of the exam
- Electronics7% of the exam
- Power Systems8% of the exam
- Electromagnetics4% of the exam
- Control Systems6% of the exam
- Communications5% of the exam
- Computer Networks4% of the exam
- Digital Systems8% of the exam
- Computer Systems5% of the exam
- Software Engineering4% of the exam
Also: 15 free questions across all topics, the FE cheat sheet and the study guide.
Get Engineering Economics exam-ready
The full FE bank has 30 Engineering Economics questions. Timed practice exams match the real exam's length and domain weights, every result shows your score per domain, and Review Mode re-drills the questions you missed.
Not affiliated with NCEES; questions are original, written from the official exam outline, and never copied from the real exam.