10 free Engineering Management questions for the FE Industrial and Systems Exam (FE) exam, each with the correct answer and an explanation for every option.

What this domain covers

Running people and projects: management principles, organisational behaviour, project scheduling and performance measurement.

Exam weight
8%
On a real exam
≈ 9 questions
In our bank
48 questions

Topics that come up most

  • Critical path method and PERT estimates
  • Project crashing and earned value
  • Organisational structures and leadership
  • Motivation theories and team behaviour
  • Performance measures and productivity

How to study it

Draw a few small activity networks and compute early and late start times and float by hand until it is routine; CPM questions reward speed.

Sample Engineering Management questions

Try each one before opening the answer. Original questions written to the official exam objectives.

  1. Question 1

    In a project schedule, a milestone is best defined as:

    • AAn activity with zero total float
    • BThe activity with the longest duration
    • CA summary task grouping work packages
    • DA significant event with zero duration
    Show answer and explanation

    Answer: D) A significant event with zero duration

    A milestone is a zero-duration event that marks a significant point in the schedule. It is not an activity, so it has no duration and uses no resources.

    • AIncorrect. An activity with zero total float is a critical activity on the critical path. It still has a duration and uses resources, while a milestone takes no time.
    • BIncorrect. How long an activity takes does not make it a milestone. The longest activity may not even be on the critical path.
    • CIncorrect. A summary task rolls up the durations of the tasks under it in the work breakdown structure. A milestone has no duration and marks a single point in time.
    • DCorrect. A milestone takes no time and uses no resources. It marks a key point, such as finishing a major deliverable or passing a phase gate.
  2. Question 2

    In a PERT analysis, the critical path has two uncertain activities with variances of 4 days² and 9 days². All other critical-path activities are deterministic, and activity times are independent. The standard deviation of the project duration is about:

    • A3.6 days
    • B13 days
    • C5 days
    • D6.5 days
    Show answer and explanation

    Answer: A) 3.6 days

    For independent critical-path activities, sum the variances (4 + 9 = 13 days²) and take the square root to get the project standard deviation, about 3.6 days.

    • ACorrect. Independent variances add along the path: 4 + 9 = 13 days². The project standard deviation is √13 ≈ 3.6 days.
    • BIncorrect. 13 days² is the project variance. The standard deviation is its square root.
    • CIncorrect. This adds the individual standard deviations (2 + 3). For independent activities, add the variances instead, then take the square root.
    • DIncorrect. This averages the two variances. Variances along a path are summed, not averaged, and the result must then be square-rooted.
  3. Question 3

    A project team has 6 members. The number of possible two-way communication channels is:

    • A15
    • B30
    • C6
    • D36
    Show answer and explanation

    Answer: A) 15

    • ACorrect. n(n − 1)/2 = 6(5)/2.
    • BIncorrect. Divide by 2.
    • CIncorrect. Use n(n − 1)/2.
    • DIncorrect. Use n(n − 1)/2.
  4. Question 4

    A team is building a RACI matrix for a facility relayout project. For the task "approve final layout," one person must approve the work done by others and answer for the result. Which RACI code should that person get for this task?

    • AResponsible (R)
    • BAccountable (A)
    • CConsulted (C)
    • DInformed (I)
    Show answer and explanation

    Answer: B) Accountable (A)

    In a RACI matrix, Responsible people do the work, the Accountable person approves it and answers for the result, Consulted people give input, and Informed people are kept up to date.

    • AIncorrect. The Responsible person does the work. The work is then approved by the person who is Accountable.
    • BCorrect. The Accountable person approves the work done by the Responsible person and answers for the result.
    • CIncorrect. Consulted people give their opinion while the work is being done, through two-way communication. They do not approve it.
    • DIncorrect. Informed people are kept up to date on progress or results through one-way communication. They do not approve the work.
  5. Question 5

    In Maslow's hierarchy of needs, the highest level is:

    • ASelf-actualization
    • BSafety
    • CPhysiological needs
    • DSocial belonging
    Show answer and explanation

    Answer: A) Self-actualization

    • ACorrect. Physiological needs form the base.
    • BIncorrect. That's a lower level.
    • CIncorrect. That's the base.
    • DIncorrect. That's a middle level.
  6. Question 6

    In goal setting, the acronym SMART stands for goals that are specific, measurable, achievable, relevant and:

    • ATime-bound
    • BTentative
    • CTheoretical
    • DTiered
    Show answer and explanation

    Answer: A) Time-bound

    • ACorrect. Deadlines make goals actionable.
    • BIncorrect. It's time-bound.
    • CIncorrect. It's time-bound.
    • DIncorrect. It's time-bound.
  7. Question 7

    Buying insurance to cover a project risk is an example of risk:

    • AAvoidance
    • BTransfer
    • CAcceptance
    • DMitigation
    Show answer and explanation

    Answer: B) Transfer

    • AIncorrect. Avoidance removes the risk's source.
    • BCorrect. The financial impact shifts to the insurer.
    • CIncorrect. Acceptance takes the risk on.
    • DIncorrect. Mitigation reduces probability or impact.
  8. Question 8

    Under uncertainty, the maximax criterion chooses the alternative with the:

    • AHighest probability
    • BBest worst-case outcome
    • CSmallest maximum regret
    • DBest possible outcome
    Show answer and explanation

    Answer: D) Best possible outcome

    • AIncorrect. It ignores probabilities.
    • BIncorrect. That's maximin.
    • CIncorrect. That's minimax regret.
    • DCorrect. It's an optimistic criterion.
  9. Question 9

    In Herzberg's two-factor theory, motivators include:

    • AWorking conditions only
    • BSalary and job security
    • CAchievement and recognition
    • DCompany policies
    Show answer and explanation

    Answer: C) Achievement and recognition

    • AIncorrect. That's hygiene.
    • BIncorrect. Those are hygiene factors.
    • CCorrect. Salary is a hygiene factor.
    • DIncorrect. That's hygiene.
  10. Question 10

    The Delphi technique produces forecasts by:

    • AFitting a regression line
    • BIterating anonymous expert opinions toward consensus
    • CAveraging the last three periods
    • DSurveying all customers
    Show answer and explanation

    Answer: B) Iterating anonymous expert opinions toward consensus

    • AIncorrect. It's expert-judgment-based.
    • BCorrect. Anonymity limits dominance by individuals.
    • CIncorrect. That's a moving average.
    • DIncorrect. It uses a panel of experts.

Engineering Management: FAQs

How much of the FE exam is Engineering Management?

Engineering Management is 8% of the FE exam by the official exam guide's weighting, which on a 110-question form works out to roughly 9 questions. The real exam's exact split varies by form.

What does the Engineering Management domain cover?

Running people and projects: management principles, organisational behaviour, project scheduling and performance measurement.

How should I study Engineering Management for FE?

Draw a few small activity networks and compute early and late start times and float by hand until it is routine; CPM questions reward speed.

Where can I practise more Engineering Management questions?

This page has 10 free Engineering Management questions with answers. The ExamWize FE question bank has 48 questions in this domain. Every practice exam result breaks your score down by domain, and Review Mode re-drills the questions you missed.

Get Engineering Management exam-ready

The full FE bank has 48 Engineering Management questions. Timed practice exams match the real exam's length and domain weights, every result shows your score per domain, and Review Mode re-drills the questions you missed.

Not affiliated with NCEES; questions are original, written from the official exam outline, and never copied from the real exam.