Skip to main content

NCEES · FE

FE Industrial & Systems practice questions with answers

15 free practice questions for the FE Industrial and Systems Exam (FE), spread across the exam's topics. Try each one, then open the answer to see why every option is right or wrong.

  1. Question 1 · Mathematics

    Evaluate \(\int_0^2 (2x + 1)\,dx\).

    • A4
    • B5
    • C6
    • D10
    Show answer and explanation

    Answer: C) 6

    • AIncorrect. Include the +x term.
    • BIncorrect. That's the integrand at x = 2.
    • CCorrect. \([x^2 + x]_0^2 = 4 + 2\).
    • DIncorrect. Recheck the antiderivative.
  2. Question 2 · Engineering Sciences

    How much heat is required to raise the temperature of 5 kg of steel (specific heat c = 0.5 kJ/(kg·K)) by 100 K?

    • A500 kJ
    • B250 kJ
    • C1,000 kJ
    • D50 kJ
    Show answer and explanation

    Answer: B) 250 kJ

    Sensible heat is Q = mcΔT. Multiplying 5 kg by 0.5 kJ/(kg·K) by 100 K gives 250 kJ.

    • AIncorrect. This leaves out the specific heat (5 × 100 = 500). The heat required is Q = mcΔT, so c must be included.
    • BCorrect. Q = mcΔT = 5 kg × 0.5 kJ/(kg·K) × 100 K = 250 kJ.
    • CIncorrect. This divides by the specific heat instead of multiplying (5 × 100 / 0.5 = 1,000).
    • DIncorrect. This leaves out the mass (0.5 × 100 = 50), which gives the heat per kilogram rather than for the full 5 kg.
  3. Question 3 · Ethics and Professional Practice

    A licensed PE supervises an engineer who passed the FE exam two years ago but is not yet licensed. The PE approves a client proposal that lists the engineer as "Jordan Lee, P.E." Under the NCEES Model Rules, the PE's approval is best described as:

    • APermitting misrepresentation of an associate's professional qualifications
    • BAn undisclosed conflict of interest affecting the PE's judgment
    • CImproper sealing of documents not prepared under responsible charge
    • DAcceptable conduct, since the engineer works under the PE's supervision
    Show answer and explanation

    Answer: A) Permitting misrepresentation of an associate's professional qualifications

    The NCEES Model Rules bar licensees from falsifying or permitting misrepresentation of their own or their associates' professional qualifications. A PE who approves listing an unlicensed engineer as a 'P.E.' violates that rule, even when the engineer works under the PE's supervision.

    • ACorrect. The Model Rules state that licensees shall not falsify or permit misrepresentation of their, or their associates', academic or professional qualifications. Listing an unlicensed engineer as a P.E. misstates that person's credentials, and the PE allowed it.
    • BIncorrect. A conflict of interest involves a business or financial interest that could influence the licensee's judgment. Nothing in the scenario creates such an interest. The problem is a false statement of credentials.
    • CIncorrect. Nothing was sealed, and the engineer works under the PE's supervision. Rules on sealing and responsible charge do not apply here. The violation is the false P.E. title in the proposal.
    • DIncorrect. Working under a PE's supervision lets an unlicensed engineer do engineering work, but it does not give that person the P.E. title. Only a licensed professional engineer may use it, so presenting the engineer as a P.E. misrepresents their qualifications.
  4. Question 4 · Engineering Economics

    At 8%, with (P/A, 8%, 6) = 4.623, the present worth of $500 per year for 6 years is about:

    • A$108
    • B$3,000, ignoring interest
    • C$2,312
    • D$3,668
    Show answer and explanation

    Answer: C) $2,312

    • AIncorrect. That divides.
    • BIncorrect. Discounting lowers it.
    • CCorrect. 500 × 4.623.
    • DIncorrect. That's a future worth.
  5. Question 5 · Engineering Economics

    A machine costs $10,000 and will be sold for $2,000 at the end of its 4-year life. At 12% interest, with (A/P, 12%, 4) = 0.3292 and (A/F, 12%, 4) = 0.2092, what is the equivalent annual cost of owning the machine?

    • A$3,292
    • B$2,874
    • C$2,634
    • D$3,710
    Show answer and explanation

    Answer: B) $2,874

    EAC = P(A/P,i,n) − S(A/F,i,n) = 3,292 − 418 = $2,874. The annualized salvage value is a credit against the annualized first cost.

    • AIncorrect. This annualizes the first cost but leaves out the credit for the $2,000 salvage value.
    • BCorrect. EAC = 10,000(0.3292) − 2,000(0.2092) = 3,292 − 418 = $2,874. Equivalently, (10,000 − 2,000)(0.3292) + 2,000(0.12) = $2,874.
    • CIncorrect. This applies the A/P factor to the net cost of $8,000 and leaves out the interest on the money tied up in the salvage value (2,000 × 0.12 = $240).
    • DIncorrect. This adds the annualized salvage value instead of subtracting it. Salvage is a cash inflow, so it lowers the annual cost.
  6. Question 6 · Probability and Statistics

    A test score of 130 comes from a normal distribution with mean 100 and standard deviation 15. Its z-score is:

    • A2
    • B30
    • C0.5
    • D1.3
    Show answer and explanation

    Answer: A) 2

    • ACorrect. (130 − 100)/15.
    • BIncorrect. Divide by σ.
    • CIncorrect. That's inverted.
    • DIncorrect. Subtract the mean first.
  7. Question 7 · Probability and Statistics

    A one-sample t-test with n = 10 observations has how many degrees of freedom?

    • A10
    • B9
    • C11
    • D8
    Show answer and explanation

    Answer: B) 9

    • AIncorrect. Subtract 1.
    • BCorrect. df = n − 1 = 10 − 1.
    • CIncorrect. Subtract 1.
    • DIncorrect. Only one parameter is estimated.
  8. Question 8 · Modeling and Quantitative Analysis

    An M/M/1 queue has λ = 8 per hour and μ = 10 per hour. The average time a customer spends in the system is:

    • A0.5 hour
    • B0.8 hour
    • C0.1 hour
    • D4 hours
    Show answer and explanation

    Answer: A) 0.5 hour

    • ACorrect. W = 1/(μ − λ) = 1/2.
    • BIncorrect. That's utilization, not time.
    • CIncorrect. That's the mean service time.
    • DIncorrect. That's L, the number in the system.
  9. Question 9 · Engineering Management

    Resource leveling in project scheduling:

    • ASmooths resource use, possibly extending the schedule
    • BAlways shortens the project
    • CRemoves all float
    • DIgnores resource limits
    Show answer and explanation

    Answer: A) Smooths resource use, possibly extending the schedule

    • ACorrect. It reduces peaks and valleys.
    • BIncorrect. It may lengthen it.
    • CIncorrect. It uses float.
    • DIncorrect. It addresses them.
  10. Question 10 · Manufacturing, Service, and Other Production Systems

    In aggregate planning, a level strategy:

    • AChanges output to match demand each period
    • BKeeps output constant
    • CUses only overtime
    • DStops production in slow months
    Show answer and explanation

    Answer: B) Keeps output constant

    • AIncorrect. That's chase.
    • BCorrect. Inventory absorbs demand swings; a chase strategy matches output to demand.
    • CIncorrect. That's one tactic.
    • DIncorrect. That isn't level.
  11. Question 11 · Facilities and Supply Chain

    In locational break-even analysis, the preferred site at a given volume is the one with the:

    • ALowest fixed cost always
    • BLowest total cost at that volume
    • CHighest variable cost
    • DLargest land area
    Show answer and explanation

    Answer: B) Lowest total cost at that volume

    • AIncorrect. Variable cost matters at high volume.
    • BCorrect. Total cost = fixed + variable × volume.
    • CIncorrect. That raises total cost.
    • DIncorrect. That isn't the criterion.
  12. Question 12 · Human Factors, Ergonomics, and Safety

    Acclimatization to working in heat typically takes about:

    • A1 to 2 weeks
    • B1 hour
    • C6 months
    • DIt never occurs
    Show answer and explanation

    Answer: A) 1 to 2 weeks

    • ACorrect. Gradual exposure builds tolerance.
    • BIncorrect. That's too short.
    • CIncorrect. It's much faster.
    • DIncorrect. People do acclimatize.
  13. Question 13 · Work Design

    In a time study, the observed time for an element is 2.0 minutes, the performance rating is 110%, and allowances are 15% of normal time. The standard time is about:

    • A2.20 minutes
    • B2.53 minutes
    • C2.30 minutes
    • D1.91 minutes
    Show answer and explanation

    Answer: B) 2.53 minutes

    Normal time = observed time × rating = 2.0 × 1.10 = 2.20 min. Standard time = normal time × (1 + allowance) = 2.20 × 1.15 ≈ 2.53 min.

    • AIncorrect. 2.0 × 1.10 = 2.20 min is the normal time. The allowances have not been added yet.
    • BCorrect. Normal time = 2.0 × 1.10 = 2.20 min. Standard time = 2.20 × (1 + 0.15) ≈ 2.53 min.
    • CIncorrect. 2.0 × 1.15 = 2.30 min applies the allowances but leaves out the 110% performance rating.
    • DIncorrect. 2.20 / 1.15 ≈ 1.91 min divides the normal time by the allowance factor. Allowances increase the time, so you multiply by 1.15.
  14. Question 14 · Quality

    A quality team has tallied six months of customer complaints by complaint type. Which purpose does a Pareto chart of these data serve?

    • ACompare the process spread with the specification limits
    • BRank complaint types to show which few account for most
    • CTrack a complaint rate over time against control limits
    • DOrganize possible root causes into branches by category
    Show answer and explanation

    Answer: B) Rank complaint types to show which few account for most

    A Pareto chart ranks categories by frequency in descending order to show the vital few that cause most problems. Capability studies, control charts and fishbone diagrams do other jobs.

    • AIncorrect. Comparing process spread with specification limits is process capability analysis (for example, Cp and Cpk), not a Pareto chart.
    • BCorrect. A Pareto chart puts the categories in descending order of frequency, usually with a cumulative line. This shows the vital few categories that cause most of the problem, so the team can focus there first.
    • CIncorrect. Plotting a statistic over time against control limits is what a control chart does. A Pareto chart has no time axis and no control limits.
    • DIncorrect. Grouping possible causes into branches (for example, man, machine, method, material) is a cause-and-effect (fishbone) diagram.
  15. Question 15 · Systems Engineering, Analysis, and Design

    Two identical exponential units in active parallel each have λ = 0.01 per hour. The system MTBF is:

    • A100 hours, one unit
    • B150 hours
    • C200 hours, standby
    • D50 hours
    Show answer and explanation

    Answer: B) 150 hours

    • AIncorrect. Redundancy adds life.
    • BCorrect. For two active parallel units, MTBF = 1.5/λ = 1.5/0.01.
    • CIncorrect. That's for perfect standby.
    • DIncorrect. That's series.

Ready for a full FE practice exam?

These are a sample from the ExamWize question bank. Full practice exams match the real exam's length, time limit and topic weights, with every answer explained.

Original questions written from the official exam outline. Not affiliated with NCEES; never copied from the real exam.