ASP11 · 7% of the exam
Environmental Management practice questions
10 free Environmental Management questions for the Associate Safety Professional (ASP) (ASP11) exam, each with the correct answer and an explanation for every option.
What this domain covers
The environmental side of the role: the main US environmental laws, waste handling, spill prevention and environmental management systems.
- Exam weight
- 7%
- On a real exam
- ≈ 14 questions
- In our bank
- 41 questions
Topics that come up most
- RCRA hazardous waste identification and management
- CERCLA and EPCRA reporting
- Clean Air Act and Clean Water Act basics
- Spill prevention and SPCC plans
- ISO 14001 environmental management systems
How to study it
Make a one-line summary of what each major EPA law controls and who it applies to; questions often ask which law governs a described situation.
Sample Environmental Management questions
Try each one before opening the answer. Original questions written to the official exam objectives.
Question 1
Used batteries and fluorescent lamps are often managed under streamlined rules as:
- ARadioactive waste
- BMunicipal trash
- CMedical waste
- DUniversal waste
Show answer and explanation
Answer: D) Universal waste
- AIncorrect. That's a different category.
- BIncorrect. They need special handling.
- CIncorrect. That's a different category.
- DCorrect. A simplified hazardous waste category.
Question 2
A metal finishing plant sends its process wastewater into a city sewer that leads to a publicly owned treatment works (POTW); it does not discharge directly to a river. Which Clean Water Act requirements most directly govern this discharge?
- ANational Pretreatment Program standards, including categorical limits and POTW local limits
- BAn NPDES permit issued to the plant for each outfall into the sewer
- CA Spill Prevention, Control, and Countermeasure plan covering the wastewater
- DStormwater pollution prevention plan limits for the process wastewater
Show answer and explanation
Answer: A) National Pretreatment Program standards, including categorical limits and POTW local limits
Indirect dischargers to a POTW must meet National Pretreatment Program requirements: general and specific prohibitions, EPA categorical standards, and local limits developed by the POTW.
- ACorrect. Under 40 CFR 403, industrial users that discharge to a POTW must meet the general and specific prohibitions and any categorical pretreatment standards. Local limits set by the POTW also count as pretreatment standards.
- BIncorrect. NPDES permits cover point-source discharges directly to waters of the United States. A discharge into a POTW is an indirect discharge, which is controlled through pretreatment requirements.
- CIncorrect. SPCC plans deal with preventing oil spills from storage containers. They do not set limits on routine process wastewater sent to a sewer.
- DIncorrect. Stormwater plans deal with runoff from industrial activity. Process wastewater sent to a POTW falls under the pretreatment program.
Question 3
A safety professional is designing an uncovered dike around several outdoor bulk oil storage tanks. Which capacity is the commonly used design rule of thumb for this secondary containment?
- A50% of the combined volume of all tanks inside the dike
- B10% of the volume of the largest tank inside the dike
- C110% of the volume of the largest tank inside the dike
- D100% of the combined volume of all tanks inside the dike
Show answer and explanation
Answer: C) 110% of the volume of the largest tank inside the dike
SPCC rules require secondary containment for 100% of the largest single container plus freeboard for precipitation, so outdoor dikes are commonly sized to 110% of the largest tank. Other programs differ; for example, RCRA container storage uses the greater of 10% of total volume or 100% of the largest container.
- AIncorrect. Bulk oil containment is sized from the single largest container, not a fraction of the combined volume. Half of the total could be less than one full tank failure in some layouts, and more than needed in others.
- BIncorrect. This could not hold a catastrophic failure of the largest tank. SPCC (40 CFR 112.8(c)(2)) requires capacity for the entire contents of the largest single container. A 10% figure appears only in RCRA container-storage rules, and there it applies to total volume, compared against the largest container.
- CCorrect. SPCC (40 CFR 112.8(c)(2)) requires secondary containment for the entire capacity of the largest single container plus enough freeboard to hold precipitation. Sizing an uncovered dike to 110% of the largest tank is the common practical way to provide that freeboard, and some state and local rules require it.
- DIncorrect. Containment is based on the largest single container, because simultaneous failure of every tank is not the design case. Sizing for the combined volume goes beyond the common rule, and it still allows no freeboard for rainwater in an uncovered dike.
Question 4
ISO 14001 is an international standard for:
- AOccupational health and safety
- BEnvironmental management
- CQuality management
- DInformation security
Show answer and explanation
Answer: B) Environmental management
- AIncorrect. That's ISO 45001.
- BCorrect. It uses plan-do-check-act.
- CIncorrect. That's ISO 9001.
- DIncorrect. That's ISO 27001.
Question 5
Under RCRA, a solid waste can be a hazardous waste because it is "listed" or because it shows a hazardous characteristic. Which of the following identifies the LISTED hazardous wastes?
- AThe ignitability, corrosivity, reactivity and toxicity criteria
- BThe F, K, P and U lists in 40 CFR Part 261, Subpart D
- CThe CERCLA hazardous substance list with reportable quantities
- DThe EPCRA Section 313 toxic chemical release inventory list
Show answer and explanation
Answer: B) The F, K, P and U lists in 40 CFR Part 261, Subpart D
RCRA listed hazardous wastes are on the F (non-specific source), K (specific source), P (acute) and U (toxic) lists in 40 CFR 261 Subpart D. Characteristic wastes are identified by ignitability, corrosivity, reactivity or toxicity.
- AIncorrect. These are the four RCRA characteristics. They identify characteristic hazardous wastes, not listed wastes.
- BCorrect. F covers non-specific-source wastes and K covers specific-source wastes. P and U (§261.33) cover discarded commercial chemical products: P-list wastes are acute hazardous wastes and U-list wastes are toxic wastes.
- CIncorrect. The CERCLA list sets reportable quantities for release reporting. It does not decide which wastes are RCRA listed hazardous wastes.
- DIncorrect. The Section 313 list sets which chemicals must be reported in annual release inventories. It is not used to classify RCRA listed wastes.
Question 6
In carbon accounting, Scope 1 emissions are:
- ADirect emissions
- BPurchased electricity
- CSupply chain emissions
- DEmployee commutes only
Show answer and explanation
Answer: A) Direct emissions
- ACorrect. From sources the organization owns or controls.
- BIncorrect. That's Scope 2.
- CIncorrect. That's Scope 3.
- DIncorrect. That's part of Scope 3.
Question 7
A large quantity generator keeps hazardous waste in containers in its central accumulation area. Under 40 CFR 262.17, which practice meets the container requirements?
- AContainers stay open during production hours for convenience and are closed at the end of each shift
- BContainers stay closed except when adding or removing waste and are marked with "Hazardous Waste," the hazards, and the accumulation start date
- CContainers are marked with the words "Hazardous Waste" when filling begins, and the accumulation start date is added when the waste is shipped
- DContainers are kept closed and marked, and waste may be held on site for up to 180 days without a permit
Show answer and explanation
Answer: B) Containers stay closed except when adding or removing waste and are marked with "Hazardous Waste," the hazards, and the accumulation start date
Under 40 CFR 262.17, large quantity generator containers must stay closed except when waste is added or removed. They must be marked "Hazardous Waste" with a hazard indication and the accumulation start date, and waste may be held for no more than 90 days.
- AIncorrect. Containers must always be closed during accumulation, except when waste is being added or removed. Leaving them open for a whole shift does not comply.
- BCorrect. Section 262.17 requires containers to be closed except when waste is being added or removed. Each container must be marked with the words "Hazardous Waste," an indication of the hazards of the contents, and the date accumulation began, clearly visible for inspection.
- CIncorrect. The accumulation start date must be clearly visible on each container during accumulation so the 90-day limit can be checked. A hazard indication is also required.
- DIncorrect. A large quantity generator may accumulate waste for no more than 90 days without a permit. The 180-day period applies to small quantity generators.
Question 8
A vehicle maintenance facility routes its wash-bay and floor-drain water through an oil-water separator before the water leaves the site. What is this unit's main function?
- ARaise or lower the wastewater pH into an acceptable range before discharge
- BPhysically separate oil from the wastewater so it can be removed before discharge
- CPrecipitate dissolved heavy metals from the wastewater as a removable sludge
- DDestroy dissolved organic solvents in the wastewater through chemical oxidation
Show answer and explanation
Answer: B) Physically separate oil from the wastewater so it can be removed before discharge
An oil-water separator is wastewater treatment equipment that separates oil from water so the oil can be removed before the water is discharged. It does not neutralize pH, remove dissolved metals, or oxidize dissolved organics.
- AIncorrect. Adjusting pH is done by chemical neutralization, not by an oil-water separator.
- BCorrect. Federal regulations define an oil-water separator as wastewater treatment equipment that separates oil from water. It uses a separation tank with parts such as skimmers, weirs and sludge hoppers.
- CIncorrect. Removing dissolved metals takes chemical treatment such as precipitation. A separator removes oil that separates out of the water.
- DIncorrect. Chemical oxidation is a separate treatment process. An oil-water separator works physically, by separating oil from water, and does not destroy dissolved organics.
Question 9
A generator is shipping hazardous waste offsite for disposal. Which statement best describes the role of the Uniform Hazardous Waste Manifest (EPA Form 8700-22)?
- AIt is filed with EPA after disposal is complete, so the generator does not sign it before the waste leaves the site.
- BIt is prepared by the transporter, who chooses the receiving facility and keeps the generator's copy on the truck.
- CIt goes with the shipment and is signed by the generator, transporter and designated facility, tracking the waste from generation to final destination.
- DIt is used for waste sent to recyclers, while waste sent for disposal is tracked on a standard bill of lading.
Show answer and explanation
Answer: C) It goes with the shipment and is signed by the generator, transporter and designated facility, tracking the waste from generation to final destination.
The hazardous waste manifest is prepared by the generator and signed by each party that handles the waste. It tracks the shipment from generation to the designated facility (cradle to grave).
- AIncorrect. Under § 262.23, the generator must hand-sign the manifest certification and get the initial transporter's signature and acceptance date before the waste leaves the site.
- BIncorrect. Under § 262.20, the generator prepares the manifest and must designate a permitted facility on it. The generator keeps one copy and gives the remaining copies to the transporter.
- CCorrect. The manifest is RCRA's cradle-to-grave tracking document. The generator and transporter sign it at pickup, and the designated facility signs it on receipt. A large quantity generator that doesn't get the signed copy back must follow up within 35 days and file an Exception Report within 45 days (§ 262.42).
- DIncorrect. Under § 262.20(a), any generator that transports or offers hazardous waste for offsite treatment, storage or disposal must prepare a manifest. A bill of lading does not replace it.
Question 10
A manufacturer wants a life cycle assessment comparing two product designs. The study must include raw material extraction, manufacturing, transport, product use, and end-of-life disposal. Which system boundary fits this scope?
- ACradle-to-gate
- BGate-to-gate
- CCradle-to-grave
- DGate-to-grave
Show answer and explanation
Answer: C) Cradle-to-grave
A cradle-to-grave LCA covers every stage from raw material extraction through disposal. Cradle-to-gate, gate-to-gate and gate-to-grave each cover only part of the life cycle.
- AIncorrect. Cradle-to-gate covers resource extraction and manufacturing only up to the point where the product leaves the factory gate. It leaves out use and disposal.
- BIncorrect. Gate-to-gate looks at one module or process inside the life cycle, such as a single manufacturing step. It does not cover the whole product life.
- CCorrect. Cradle-to-grave covers the full life cycle, from the raw material extraction stage through the end-of-life stage, including disposal.
- DIncorrect. Gate-to-grave starts after the product leaves the factory gate. It leaves out raw material extraction and manufacturing.
Environmental Management: FAQs
How much of the ASP11 exam is Environmental Management?
Environmental Management is 7% of the ASP11 exam by the official exam guide's weighting, which on a 200-question form works out to roughly 14 questions. The real exam's exact split varies by form.
What does the Environmental Management domain cover?
The environmental side of the role: the main US environmental laws, waste handling, spill prevention and environmental management systems.
How should I study Environmental Management for ASP11?
Make a one-line summary of what each major EPA law controls and who it applies to; questions often ask which law governs a described situation.
Where can I practise more Environmental Management questions?
This page has 10 free Environmental Management questions with answers. The ExamWize ASP11 question bank has 41 questions in this domain. Every practice exam result breaks your score down by domain, and Review Mode re-drills the questions you missed.
Other ASP11 topics
- Mathematical Calculations10% of the exam
- Safety Programs and Concepts25% of the exam
- Ergonomics8% of the exam
- Fire Prevention and Protection12% of the exam
- Emergency Preparedness and Response10% of the exam
- Industrial Hygiene and Occupational Health12% of the exam
- Training, Education, and Communication11% of the exam
- Legal5% of the exam
Also: 15 free questions across all topics, the ASP11 cheat sheet and the study guide.
Get Environmental Management exam-ready